Welcome to our blog documenting the construction of two new houses in Asylum Road, Peckham. The design of the scheme can be seen on our website.

These have been named the Laundry Houses. During the design phases of the project, we found that there had been a laundry on the site of Albert Way, the road that the new houses will open onto. The laundry theme has informed the material and design decisions we have been making.

Over the coming months we will be posting photographs of the construction process and images of things that have influenced and informed the design.

Come back regularly to follow our progress, or visit www.quay2c.com to find out more about us and our work.

Showing posts with label timber cladding. Show all posts
Showing posts with label timber cladding. Show all posts

Monday, 28 July 2014


Out larch cladding to the back courtyards being installed & looking good. They are being co-ordinated carefully by David and Michael to tie into the cladding of the plant boxes below. 

Our sandblasted glass cladding fully taking shape.
Unknown to us the glass is pretty similar to the New Steven Holl designed art school opposite the Mackintosh in Glasgow. The cranes in the reflection were giving access the other week when we were there to strip out the debris from the awful fire that sadly took out the amazing library of one of my favourite buildings. 

Thursday, 19 June 2014

The glass cladding of our first floor pods has started in a sand blasted light green finish to tone in with the trees and the garden


Eyeing up the gap

The timber fins appearing on the rear elevation

Friday, 2 May 2014


Camaru cladding boards fixed down no 18 AR side
 Camaru cladding boards fixed down no 14 AR side
Plastering starting in the kitchen and lots of light coming in the rooflights in the lobby behind. 

A 2m2 sample of the oak engineered timber floor boards to be used throughout both houses
The utility room "kit" is appearing

The basement bathrooms are progressing

All the rooflights are now in and working wonders even in the rain 



Monday, 14 April 2014

Not much blogging as I managed to break my leg and ended up in hospital for 12 nights! however not before I got my show Veils and Repetitions up in the m2 gallery which is on till the 6th May

Rooflights will have glass in this week !

View to the gardens with all their walls now pretty complete
Underside of the G-1st stairs with temporary treads. Oak infills will be inset betweenthe steel ribs

General view of stair. Ultimately the treads will float 40 mm off the fair faced timber walls on each side.

Detail

New laser cut and painted open tread stairs now in awaiting finished oak treads




Camaru timber cladding now on site.

Tuesday, 28 January 2014

Example of camaru timber cladding now on order that sits above the brickwork garden walls

Brickwork garden wall to no 18 Asylum Rd side.

Brickwork garden wall to no 18 Asylum Rd now nearing completion.