Welcome to our blog documenting the construction of two new houses in Asylum Road, Peckham. The design of the scheme can be seen on our website.

These have been named the Laundry Houses. During the design phases of the project, we found that there had been a laundry on the site of Albert Way, the road that the new houses will open onto. The laundry theme has informed the material and design decisions we have been making.

Over the coming months we will be posting photographs of the construction process and images of things that have influenced and informed the design.

Come back regularly to follow our progress, or visit www.quay2c.com to find out more about us and our work.

Friday, 12 July 2013

One off Basements Team inspecting the concrete pour and vertical pre cast panels.

Pre cast vertical panels being secured by in situ cast concrete slab floor.

Pre cast panels now on site

Thursday, 4 July 2013

.

The first of our pre cast panels arriving at site today ready to shore up the the boundary basement walls.

.

A pic from Chris on site showing a trench box being maneuvered in.

Wednesday, 3 July 2013

.

The final bit of foundation for the back brickwork garden walls being formed.

.

We now have a working area to no 18 Asylum Rd and the site is looking nice and clear to begin putting trench boxes in along the boundary walls. The pre cast panels will start arriving tomorrow !