Welcome to our blog documenting the construction of two new houses in Asylum Road, Peckham. The design of the scheme can be seen on our website.
These have been named the Laundry Houses. During the design phases of the project, we found that there had been a laundry on the site of Albert Way, the road that the new houses will open onto. The laundry theme has informed the material and design decisions we have been making.
Over the coming months we will be posting photographs of the construction process and images of things that have influenced and informed the design.
Come back regularly to follow our progress, or visit www.quay2c.com to find out more about us and our work.
Thursday, 5 December 2013
![]() |
| The front view with windows now installed. |
![]() |
| The view from the kitchen towards Albert Way with the sliding doors now in. |
![]() |
| The Ground floor sliding doors now in as seen from the basement |
![]() |
Mark Cousins Architect from Edinburgh Univ School of Architecture visits site at the weekend with Julia. |
![]() |
| The view from Albert Way last weekend |
![]() |
| Our basement tanking gets nearer completion. |
![]() |
| The flat roof membrane over the ground floor awaiting sedum covering in the spring. Rooflights to the GF bathroom and lobbies temporary covered to the left. |
![]() |
| Our underfloor heating pipe has arrived to go in the basement screed |
Monday, 25 November 2013
![]() |
| The garden walls getting built. |
![]() |
| The sliding door and french doors are now in to the back garden courtyards. |
![]() |
| The sliding door |
![]() |
| The tanking membrane going down in the basement |
![]() |
| The tanking membrane with yellow bucket ! |
![]() |
| The roofing membrane on the top roof is now pretty much there. With the better weather forecast this week we are hoping to get the lower roofs well on the way to being sealed up. |
![]() |
| The windows on site |
Friday, 15 November 2013
![]() |
| Timber structure in the basement looking towards the back from the main bedroom. the staircase "slot" is on the right. |
![]() |
| The new sliding patio doors in the basement. |
![]() |
| Lights, shoes and triton waterproofing membrane |
![]() |
| Ground floor back lounge with one half of the patio door sitting where the GF shower room will be. |
![]() |
| view of the lounge looking towards the garden and terrace. |
![]() |
| the staircase "slot" from the ground floor |
Monday, 11 November 2013
![]() |
| Some "still lifes" from site over the weekend. |
![]() |
| Wood shavings on the timber ground floor |
![]() |
| Screws on the timber floor |
![]() |
| Staircase "slot" timber |
![]() |
| Shadows in the ist floor bedroom "pod" |
![]() |
| The rooflights awaiting glass tops to light the ground floor lobby and bathrooms. |
![]() |
| More late afternoon shadows |
![]() |
| The Manheim sisters visit site |
![]() |
| Our nice looking Triton waterproof tanking material is now on site to be installed in the basement. |